Ian Swinhoe, CEO of DSV Solutions AB. Photo: DSV

DSV is expanding its logistics facility in Landskrona—it will become Sweden's largest

In the fall of 2022, logistics giant DSV will break ground on a massive 175,000-square-meter construction project adjacent to its existing logistics facility in Landskrona. With this expansion, the logistics facility’s total floor space will exceed 270,000 square meters, making it Sweden’s largest and one of the largest in the Nordic region.

Centrally located between Gothenburg to the north and Lund/Malmö to the south, and right next to the E6/E20 highway, the new facility—together with the existing one—will form a logistics center serving the Danish, Finnish, Norwegian, and Swedish markets. With the new logistics buildings, DSV in Landskrona will offer a total warehouse area of over 225,000 m². Together with the existing office space of nearly 11,000 m² and a 35,000 m² terminal, DSV’s logistics center in Landskrona will cover more than 270,000 m² once the new facilities are completed. The new facility will also include 70,000 m² of temperature-controlled warehouse space.

Two new warehouses

The new 175,000 m2 construction project includes two new warehouses. The 70,000 m2 building will feature two temperature-controlled storage zones with sufficient space for storing fast-moving consumer goods, which is particularly important for supermarket chains and consumer brands. The second building, covering 105,000 m², will be used for traditional warehousing and will include a range of automated solutions.

– We will be able to offer a comprehensive temperature-controlled solution with different temperature zones, as well as additional capacity for traditional warehousing at the new DSV warehouses. “These facilities will be equipped with technology such as AGVs (Automated Guided Vehicles) and cranes, which will enable us to provide the best possible efficiency and service levels to our Nordic customers,” says Ian Swinhoe, CEO of DSV Solutions AB.

Construction is expected to begin in the fall of 2022, and occupancy of the new facilities is expected to take place in 2024, once the temperature-controlled storage areas are completed and the automation solutions are installed.

sce banner 930x180px
Ads
0d7472f9 628b 4d35 ab4f f20bc688de0b
Logistics & Transportation: Supply Chain Impact - Conversion 580x300
2026 Button Brain Ads 290x150px v02
Logistics Stockholm
2026 1 ad tgwne (290 x 150 px)

SCE WEEKLY UPDATE

Our newsletter—SCE Weekly Update—is published weekly and features relevant news about the supply chain and logistics. Sign up here!

Latest Issue

More News

SKECHERS BUILDS MEGA-STORE WITH A BUTTON

Skechers is building a new, highly automated European distribution center in Liège, Belgium. The company has selected KNAPP as its technology partner for the project, with KNAPP supplying the advanced intralogistics solutions. The facility will be put into operation in phases through mid-2030 and, starting in late 2028, will serve as a hub for Skechers’ deliveries to the entire European market …

Read more »

Management Change in Langebæk – Appoints Co-CEOs

As Langebæk A/S’s long-time CEO, Peter Gyldendal, steps down after more than 20 years, Anders Bartholin and Lars Bek Jensen have been appointed as the company’s new leadership duo. The transition comes at a time when Langebæk is performing strongly and is well positioned for the next phase of its development …

Read more »

Swedish e-commerce is exporting more and more

Swedish e-retailers are selling more and more to customers abroad. During the second quarter, Swedish e-retailers shipped 16 percent more packages to private individuals in other countries than during the same period last year. This is according to the Swedish Transport Association’s Package Index, which is now measuring e-commerce export flows for the first time …

Read more »

Sign up for the newsletter

Get this week's top news stories, expert interviews, and trends—concise and relevant—delivered straight to your inbox